The north stand of the ancient mining stadium is 90m long and 5.6m wide, with a rostrum in the middle that is 22.37m long and 5.6m wide. In June 2009, the North Stand of Gushuyuan Mine Sports Ground was renovated, and a novel and unique membrane structure was set up in the North Stand. It adopts the steel structure as the main frame of the project, the rigging adopts the steel wire rope series, the membrane material adopts Ferrari F1002T2, and the membrane material installation adopts the tension membrane technology, which makes the function of the reconstructed Gushuyuan Mine sports field more perfect.
1. Characteristics of membrane structure
The membrane structure is a brand-new structure of a new type of material. It has the following characteristics: 1) The membrane itself is very light and thin, with a weight of only 0.01kN/㎡~0.02kN/㎡. The amount of steel used is very small, which is very suitable for extra-large span structures. At present, the maximum span of membrane structure buildings has exceeded 200m. 2) The film has good light transmittance and a certain degree of heat preservation. It can pass through a lot of soft natural light, and can filter out most of the ultraviolet rays. The transmittance to natural light can reach 25%, which greatly reduces the lighting cost and heating during the day. with air conditioning costs. At the same time, the membrane has good self-cleaning properties, and the dust on the membrane surface can be washed away with rainwater. 3) The film has good durability. For example, the film with glass fiber as the base material has strong anti-aging performance, and the general service life is 20 to 30 years. 4) The cost of the structure is low, and the cost of the membrane structure building is only 1/3 to 1/2 of the cost of the traditional building structure. 5) The construction of the membrane structure is convenient, fast, and the cycle is short. Large-scale membrane structure buildings can also be completed in just a few months. 6) The membrane structure is novel and beautiful in shape, light and elegant, and the color of the membrane material can be selected, which has the artistic appeal of the times.
2. Structural construction
2.1 Preparation and acceptance of on-site assembly of steel structures
Under the conditions of construction, the construction unit will transport the tools and equipment before the assembly to the open space of the North Stand one week before the construction, and the technicians will mark, position, re-inspect and weld the supporting tire frames during the assembly of the steel structure.
2.2 Stacking requirements of components
Considering that the construction site is located in the sports field, without affecting the use of students, the construction unit selected the cement floor small basketball court empty space on the west side of the sports field as a temporary stacking site after all components passed the acceptance inspection.
2.3 Welding of steel structures
The welding sequence of steel structures should consider the factors of welding deformation, and try to use symmetrical welding. The parts with large shrinkage should be welded first. During the welding process, the heating amount should be balanced to reduce the welding deformation and shrinkage. After welding, repair and smooth the welding scar to remove welding slag and spatter.
2.4 Installation process After preliminary investigation, this project adopts the international advanced membrane material — Ferrari F1002T2 produced by the French Ferrari company. and always pre-tensioned during the coating process. The computer simulates the actual engineering, and generates a complete cutting model. According to the biaxial tensile properties of the film material, the film is cut and cut, and then installed on site.
2.5 Erection of scaffolding In order to meet the installation of the membrane structure of this project, according to the actual situation of the construction site and the requirements of relevant national construction specifications, this project adopts the erection of double-row outer scaffolding combined with full-floor scaffolding. The height of the scaffolding is controlled at about 1.8m from the top. .
2.6 Preparation of film cloth
In order to further ensure the smooth progress of the film cloth paving and tensioning work, the technicians should do some relevant preparations in advance after setting up the scaffolding: first open the film cloth gently; put it on a clean moisture-proof cloth; Fold in half on half of the longitudinal belt, clamp the film to make the film very loose; the film is in place; tie the cable in the lower bottom position; insert the edge rope to ensure that the rope fits the film; tie the rope to On the corner of the membrane cloth; at the same time, tie the rope to the higher end, so that the higher rope exceeds the membrane cloth; the latch on the steel structure must match the metal plate on the membrane cloth.
2.7 The paving of the membrane cloth This project is hoisted by a truck crane. The specific paving sequence is as follows: Lift the membrane to the designated paving position; Use cable buckles to fix the membrane initially and firmly, while keeping the membrane cloth in a relaxed state; The fixed membrane and notochord are pulled to the surrounding joints in sequence; connect the surrounding joint plates; install the cable buckle to fix the membrane cloth firmly at the end, pay special attention to the fixed membrane should also maintain a certain range of relaxation.
2.8 Tension of the membrane cloth After confirming that the laying work of the membrane cloth is completed, the technicians carefully check whether the contact surface and structural parts of the membrane cloth are firmly connected, and then further confirm that each connection point is firmly connected, and then stretch the membrane to the specified position. position, fasten it firmly with the buckle, and then put on the sling.
As the latest architectural form, the membrane structure is covered with the most advanced environmentally friendly chemical flexible membrane material. In addition to its lightness in terms of vision and weight, the translucency of the membrane material brings great vision to people. Comfortable, thereby improving free daylighting, saving daytime light energy, and effectively increasing the charm of the membrane structure stand.